Will anyone still claim that everything is fine at Kashiwazaki?
Saturday, Aug. 11, 2007
Quake-hit N-plant may be shut a year: IAEA
Kyodo News
The head of an International Atomic Energy Agency team of experts indicated Friday that it could be a year before a Niigata Prefecture nuclear power plant damaged by the July 16 earthquake can resume operations.
Speaking to reporters in Tokyo after a four-day inspection of the Kashiwazaki-Kariwa nuclear power station, Philippe Jamet said the process of restarting the plant could take "months or a year."
It is "not something you can do very fast. It was a very big earthquake," he said.
Japanese nuclear experts have said it would take at least a year to put the plant back into operation, but it was the first time that a third-party body such as the IAEA has expressed such a forecast.
Asked whether a report the IAEA will issue about damage to the plant would contain negative news for Japan, Jamet, director of the IAEA's Nuclear Installation Safety Division, said, "I'm not too worried."
Jamet suggested it would take some time before the Vienna-based U.N. nuclear watchdog publishes the report, but said, "Some information, I think, will be released fairly shortly," indicating an outline or key part may be made public soon.
But he declined comment on what he and five other members saw in the plant, which faced a radiation leak following the magnitude-6.8 quake. The plant will remain idle until the safety of its seven reactors is fully ensured.
The mission held talks Friday with plant operator Tokyo Electric Power Co. and the government's Nuclear and Industrial Safety Agency and Nuclear Safety Commission, and discussed its preliminary conclusions from the survey with the Japanese side. The delegation, consisting of two IAEA experts and four seismic safety specialists, was scheduled to leave Japan on Saturday.
Jamet hinted that the mission had heated talks with nuclear regulators and Tepco, saying, "I cannot tell you that we agreed on everything, but we had a very serious, very in-depth, technical and very fruitful confrontation.
"To a certain extent, it's our job to push them as far as we can to make sure that what they said is really trustable," he said. "So that's what happened."
Jamet said that when the IAEA makes its independent assessment of the quake-hit plant under the leadership of Director General Mohamed ElBaradei, "We are taking into account those discussions where we don't always agree."
During the four-day examination of the plant, the delegation looked inside all seven reactor buildings. But it did not see the reactor vessels, as they have remained sealed since the temblor, which killed 11 people and injured about 2,000.
Japan had initially been reluctant to allow the IAEA to inspect the plant, but changed its tune following petitions from local officials eager for a third-party assessment to allay public concerns over the safety of nuclear power plants in Japan, which have drawn criticism due to a slew of accidents and coverups.
Tepco and the nuclear regulators have emphasized that the amount of radioactivity leaked was extremely low and poses no threat to the environment and local residents.